In loving memory of Kenis D. Keathley 6/4/81 - 3/27/22 Loving father, husband, brother, friend and firewood hoarder Rest in peace, Dexterday

Knowledge with hydraulics for processor build

Discussion in 'Chainsaws and Power Equipment' started by Chris Brackbill, Jun 7, 2022.

  1. Chris Brackbill

    Chris Brackbill

    Joined:
    Jun 6, 2022
    Messages:
    4
    Likes Received:
    20
    Location:
    Lewisberry, PA
    I’m working towards building a firewood processor and am hung up on the hydraulic design. It will be a belt driven saw with a few hydraulic components. I will base the design somewhat on the Hudson Badger except, I will have an infeed table, log lift, clamp and wedge lift. My plan was to run a two stage pump for everything. The badger uses a flow control valve after the splitter valve to reduce GPM to feed the valve on the winch. I wanted to feed a flow control or priority divider off the splitter valve to send 6 GPM to a 4 spool (open center) for the hydraulics listed above. Here is where I get hung up….
    1. Do I need a power beyond for the splitter valve (first valve after the pump) or can I use open center to feed the flow divider?
    2. Do I use a flow control or priority divider valve?
    3. Do those two valves increase pressure in order for EF port to open, and could that be adjusted properly as to not put the two stage into high pressure and not build unnecessary heat.

    I have almost all the steel to start building, and I have a 22hp engine for the power plant. I’m just trying to get my head wrapped around the hydraulics so I can set a clearer path forward.

    Thank you in advanced for the help.
     
  2. Chaz

    Chaz

    Joined:
    Jan 27, 2018
    Messages:
    8,739
    Likes Received:
    61,960
    Location:
    Southwestern NY
  3. Chris Brackbill

    Chris Brackbill

    Joined:
    Jun 6, 2022
    Messages:
    4
    Likes Received:
    20
    Location:
    Lewisberry, PA
    Did some more research and it looks like the flow divider is the right choice. I want to have a more consistent flow going to my 4 spool. I haven't decided on a live deck or log lift yet. I have two Roller Stator motors off of a overhead crane assembly I scrapped. Based on the calculations, 6.3 in3/rev, they should run 300 rpms, 2000 inch lbs of torque. Whatever I decide, these motors should work. I plan to use the Prince auto cycle valve but, still not sure if it should be an open center or power beyond to the flow divider.

    For the infeed, I was thinking of building some hourglass type rollers just using sprockets of different circumferences.

    Thought process so far for hydraulics...
    28 GPM 2 stage
    Prince auto cycle PB or OC - 4.5 or 5" splitter cylinder
    6/30 priority flow divider with relief
    4 spool valve open center - wedge lift/infeed table/log clamp/log lift or live deck

    Belt driven saw will be a manual lever to pull the saw down for a cut. Going with a .404 saw due to the keyed drive sprockets being easy to find.
     
  4. Chris Brackbill

    Chris Brackbill

    Joined:
    Jun 6, 2022
    Messages:
    4
    Likes Received:
    20
    Location:
    Lewisberry, PA
    I’ve started my build. I’ve decided to put up the build on the tube. There was only one full processor build I could find, so I figured, why not.

    The first two episodes are posted. Working on the infeed table build this weekend.

     
    KsKent, Jutt, Chaz and 6 others like this.
  5. Canadian border VT

    Canadian border VT

    Joined:
    Feb 18, 2015
    Messages:
    19,620
    Likes Received:
    130,459
    Location:
    Vermont
    I can’t help but I’m following
     
    KsKent, Chaz and Chris Brackbill like this.
  6. Chris Brackbill

    Chris Brackbill

    Joined:
    Jun 6, 2022
    Messages:
    4
    Likes Received:
    20
    Location:
    Lewisberry, PA
    The infeed table is, mostly done


    Firewood Processor Build Ep 3 - The Infeed Table
     
    KsKent and JTV10 like this.
  7. FarmerJ

    FarmerJ

    Joined:
    Dec 23, 2022
    Messages:
    2,048
    Likes Received:
    12,087
    Location:
    Minnesota
    How much do you have left on this project?